Click to enlarge
August 2011
After 60 minutes of treatment.
|
THE MINING COMPANY holds 6 BLM Claims of 560 acres each.
These claims are replete with commercial and precious minerals, not
limited to gold, silver, platinum, palladium, rhodium and iridium. The value of just one claim is estimated to
be worth at least US $ 4 Billion (to a depth of 100ft).
With gold at around $1,800 opt, this valuation should be revised upward.
These mineral claims lay on an alluvial plain that is in an area where
mountains have been eroded into sand and gravel, filling a valley to
depths of 3,000 feet. The minerals have been determined to be roughly
uniform in dispersal throughout the geological area.
The mining technology required for their recovery is of the simplest
kind. Basically, it involves placer mining, where sand and gravel are
dug from the ground and processed through extraction equipment to
concentrate precious metals. The concentrate is milled and processed to
recover the precious metals. No blasting or underground work will be
required. Mining operations have to be permitted and bonded.
The project will be conducted in two main phases:
a pilot phase and a production phase.
Operations
The operations will be executed in two overlapping lines of work. First,
a pilot plant with associated laboratory will be established. It will
function to complete the engineering of the production facility. This
process is planned to be completed in month 4. Partially in parallel,
the production facilities will be established and the mine site will be
prepared. A 9-10 months time frame is estimated to complete the
production facilities. There are two components of the operations, the
mining and the processing of the ore, which will be physically separated
for several reasons (easier permitting, better security, and flexible
ore sourcing). The offset to this are higher transportation costs which
will not overcome the benefits of the separation, in particular because
the head ore will already be partially concentrated 10:1 at the mine
site.
Sales
The electroplated mud can be sold as is and may not have to be converted
into a dore bar. Most refiners (or banks) would melt the dore bar
anyway. Selling the mud directly would save THE MINING COMPANY and the
buyer one step in the processing. THE MINING COMPANY has two sales
contracts for a minimum of 100kg per month of gold and platinum each.
Additionally, THE MINING COMPANY holds two letters of intent from third
parties offering to purchase any and all production of this mine.
Several other parties have expressed their eagerness to do the same.
Preliminary contacts with a cement producer seeking to expand operations
in Arizona have also been made to find an exit for the mining
by-products, sand and gravel as well as magnetite.
A detailed Revenue/Expense plan for a five year projection is available upon request,
along with a detailed breakdown of the use of funds.
Markets
The available precious metals have ready markets. Gold, platinum and
palladium are vigorously traded and daily quotes are available online,
in major newspapers, and from stock brokerage firms throughout the
world. Predictions for prices of these metals abound and vary from
catastrophic declines to phenomenal increases. The truth is that no one,
experts included, can know for sure the future prices of precious
metals. But given recent global monetary inflation, these metals will
likely increase in price, as they always have done in times of currency
uncertainties. In addition to inflation pressures, increasing global
commodity demand will exert even more pressure on the prices of precious
metals. Rhodium is a metal unknown to the general public and it is
probably better characterized as a "rare" metal rather than a "precious"
metal. It is primarily used in the manufacture of catalytic converters
used in the automotive industry to reduce or eliminate toxic emissions
from vehicle exhaust systems. This metal is rapidly replacing platinum
as the preferred catalyst because it is more efficient and a converter
using rhodium will last the life of the vehicle. Rhodium is in short
supply and that existing supply is by many considered to be under the
control of a de-facto monopoly. Automobile manufacturers worldwide are
dependent on this monopoly for their supply. In addition, manufacturing
fuel cells requires the use of Rhodium. As fuel cell technology drives
down the price of the cells, they will become a factor in industrial
applications. The fuel cell industry will continue to grow creating an
even greater demand for Rhodium. In short, the markets for the Company's
output are well defined historically and are easily accessible.
Exits
THE MINING COMPANY holds two purchase contracts for 100kg of Platinum
and for 100kg of Gold per month by independent parties. Other parties
have indicated their desire to engage in purchase contracts. The most
desirable form of deliverable that emerged from the discussions with
potential buyers is the anode mud obtained by electroplating the leach
solution. Banks and/or refineries take the approach of melting any
intake product anyway. This way THE MINING COMPANY may be able to save
the step of creating dore bars, while delivering a desired product.
Individual Discussion
The minerals and metals that are contained in the ore will be extracted
and processed at different times. The primary focus will be originally
on gold being the most well understood precious metal in the ore.
Platinum group metals will be included shortly thereafter (2-3 months).
Other salable minerals, in particular magnetite, will be extracted in
year 2, or early year 3. The recovery of magnetite will require a more
elaborate mining infrastructure and does not offer a return on
investment as high as gold/silver and the PGMs do.
|
Exit Strategies
| Gold/Silver
|
Gold and silver are readily salable metals in refined state. We plan on
building our own laboratory right away to produce semi-refined gold
and silver with a purity of 80-90%. The product will be assayed and
delivered to one of several metal houses, including Johnson Matthey
and others, that will purchase essentially unlimited quantities. Rodney
Beyer has past experiences and industry relationships selling hundreds
of thousands ounces of silver to metal houses.
There is virtually an unlimited demand for the metal in today's
markets, private and public.
Precious metals may also be stored for future monetization and as
collateral for other projects in which THE MINING COMPANY may engage.
| PGMs
|
The platinum group metals will not be as easily sold. The recovery will
likely focus on dore bars (mixed bars of several metals with a less
then
refined purity).
One alternative will be to engage end users of these metals, e.g., car
makers, directly to engage in delivery contracts. This opportunity has
not yet been explored sufficiently.
| Magnetite
|
The primary outlet for Magnetite is as an iron ore resource. It must be
extracted, washed, and otherwise preprocessed to obtain a salable
product, in this case with up to 70% iron content. Industry standard is
in the mid 60%. However, the equipment needed for the tonnage
required to make enough salable product is much more involved than
for the precious metals recovery, and thus, while profitable, has a
lesser margin. This mineral will be mined at a more advanced stage of
the project.
One alternative use of magnetite is as a mix-in component of specialty
concrete requiring greater hardness. It may be possible to use some
quantities for this purpose, yet here again, the margin is less than the
precious metals recovery, and thus, this may not be our initial focus.
|
Loan Repayment
Draws on the line of credit would be made over the course of several
months in the first year matching milestones to be achieved. The
repayment of the loan will occur in the second year coinciding with the
start of the first full production line. The loan can be paid back
within the 24 months time window without unduly impacting the ongoing
operations or profits of the mine.
Actual payments may vary. The loan terms are unknown at this time and
are assumed to be around 12% including all upfront points. An additional
maximum of 10% upfront financing fee is build into the pro forma
financials separate from the loan repayment schedule to satisfy the need
for compensation of intermediaries.
The burden of loan repayment will roughly be two parts repayment to one
part profits between Month 13 and Month 18 of the project. This burden
will drop to roughly one part repayment to four parts profits once the
300,000 ton per month level will be achieved between Month 18 and Month
24.
Each claim encompasses an area of 560ac. The claims are virgin dessert
land and no ongoing disturbances occur. The claims have been valued by
an independent geologist.
The claims are located atop a major magnetite bearing alluvial flat
("black sands"). The material is well rounded and granular between 1/16
mm and 2.5 cm. It is loose and can easily be separated into fractions by
simple physical means. Geological assessments have found the sediment
to be remarkably uniform in composition in horizontal as well as
vertical extent.
Extensive matrix core drilling in this area and on the claims themselves
have not reached bedrock, indicating a minimum depth of the sediment of
at least 1000 feet throughout the valley; up to 3000 ft are assumed.
While there are bedrock protrusions within the valley none are on the
claimed properties.
The area is located in an arid desert environment. The topography
consists of an alluvial plain sloping gently westward at a rate of about
50 feet per mile. Drainage, above and underground, follows the surface
slope westward. Washes crossing the claims are usually dry except for
the two rainy seasons when occasional water flow can be observed.
The area has no surface water, yet drill tests have found aquifers
between 40 and 440 feet with pump tests yielding 500 gallons per minute.
Precious metals discovered so far include
Gold (Au),
Silver (Ag),
Platinum (Pt),
Palladium (Pd),
Rhodium (Rh),
in two samples Iridium (Ir).
Assays
The assays conducted on the ore body are summarized and are
available upon request.
Resource Estimates
The Black Sands have been explored extensively. THE MINING COMPANY owns a total of present day in-ground value of close to $36.5 Billion to a depth of 100ft and $180B to a depth of 500ft.
Assays
   
Details    
   
NDNC
   
Data Room
It will cost
$250,000
to set up a mini production line, with continuous processing. An investor will receive a 5% equity position in the company for the $250,000.
The next phase will be to build a pilot plant, with the capability of processing a ton a day of ore. This will cost around
$2MM
and take between 4 to 6 months to complete and the investor will receive a 15% equity position in the company.
For $100MM
you will receive 49% of the new JV. It works on a sliding scale. For $20MM,
which is really the bottom end of an investment that would work for the project, you will get a 25% interest.
Fill out the
NDNC
and send it to me via email or FAX 1-866-592-5124, I will promptly put you in touch with the owners!
    |
|